1 VIAIP Management Letter - 2018 68.54 KB
2 VIAIP Aide Memoire Final -2018 An Implementation Support Mission from the World Bank visited Vietnam during April 17-24 and May 2-8, 2018 to carry out an overall review of the implementation of the Vietnam-Irrigated Agriculture Improvement Project 3.4 MB
3 Summary progress report, Project implementation progress report (by 31.3.2018) 44.12 KB
4 2018 PROGRESS REPORT ON PROJECT IMPLEMENTATION This report provides information on the progress, issues and recommendations regarding the Project 2.52 MB
5 VIAIP Oct 2017 MTR Mission Management Letter WB midterm review mission Management Letter 1.25 MB
6 VIAIP Oct 2017 MTR Mission Aide Memoire WB midterm review mission Aide Memoire 604.05 KB
7 VIAIP Oct 2017 MTR Mission Aide Memoire - Annexes WB midterm review mission documentation 1.2 MB
8 PROGRESS REPORT ON PROJECT IMPLEMENTATION Vietnam Irrigated Agriculture Improvement Project (VIAIP) is financed by a Credit from the International Development Association (IDA of the World Bank) and the counterpart fund from the Government of the Socialist Republic of Vietnam (GOVN). This report provides information on the progress, issues and recommendations regarding the Project until March 2017 157.67 KB
9 Biên bản ghi nhớ Đoàn công tác thực hiện dự án (9-23 tháng 5, 2016) A World Bank implementation support mission (Mission) was in Vietnam from May 9 to 23, 2016 for the Vietnam Irrigated Agriculture Improvement Project. The objective of the mission was to: i) review the overall progress of the project implementation; ii) identify bottlenecks that affecting the implementation; and iii) discuss and agree on solution to remove all issues and bottlenecks. 623.07 KB
10 Aide-memoire Implementation Support Mission (October 03-14, 2016) A World Bank Mission visited Vietnam from October 03 to 14, 2016 for the fifth implementation support mission for the Vietnam Irrigated Agriculture Improvement Project. The objectives of the Mission were to review progress of implementation, identify bottlenecks, and agree on any remedial actions. 1.07 MB
11 Aide-memoire Implementation Support Mission (September 15-25, 2015) An IDA Implementation Support Mission (ISM) was working in Vietnam during September 15-25,2015 to supervise the implementation of the Vietnam-Irrigated Agriculture Improvement Project. The objective of the mission is to carry out thorough review of the project implementation progress since the last ISM in March this year 291.33 KB
12 Project Operation Manual (POM) Attached to Decision No. 3016/ QD-BNN-HTQT dated 20/12/2013 by the Minister of Agriculture and Rural Development 773.98 KB
13 Decision 2409/QĐ-BNN-HTQT by MARD Decision approving the Feasibility Study Report of 7 provinces 12.74 MB
14 Decision approving the Feasibility Study Report Decision No. 2409 of Ministry of Agriculture and Rural Development dated 18/10/2013 approving the Feasibility Study Report of "Vietnam Irrigated Agriculture Improvement Project" funded by WB 8.56 MB
15 Loan Agreement Credit 5352-VN The Loan Agreement was signed on 24/4/2014 between "Socialist Republic of Vietnam" and "International Development Association" 5.22 MB